Wondering how we’re progressing with works at Whakawhirinaki Silverstream Pipe Bridge?
Final works to connect the pipe bridge to the drinking water network are well underway, with excavation to the existing pipes completed.
Earlier this week, we were very fortunate to have Kura and Alishia Moeahu of Te Ātiawa lead a karakia ceremony at dawn to bless the pipe bridge before it goes online, honouring the history and deep significance of Te Awa Kairangi / Hutt River and the surrounding whenua to the local iwi, Te Ātiawa.


The actual cut-in works to bring the pipe bridge online is scheduled to take place late next week. This marks a significant milestone for the project – a step forward for the region’s water supply resilience.
To carry out this work safely, traffic management on SH2 at Silverstream will remain in place until mid-October, while traffic management on Fergusson Drive will be in place until mid-November.
Watch this space for more updates on this important work. Find more info on the project via the link down below!
https://www.wellingtonwater.co.nz/projects/silverstream-pipe-bridge-project
Source: Wellington Water
25/09/25