On Sunday 23 March, resurfacing works on Ward Street will begin. The works will be carried out nightly from 6:30 PM to 6:00 AM
Below are the details of the scheduled work, including a map showing the specific areas affected.
Work Schedule
The resurfacing will be done in sections over multiple nights as follows:
- Sunday, 23 March 2025: Ward Street, between 8 Lane Street and Seddon Street (highlighted in red)
- Monday, 24 March 2025: Ward Street, between Seddon Street and 29 Ward Street (highlighted in green)
- Tuesday, 25 March 2025: Ward Street, between 3 Ward Street and 29 Ward Street (highlighted in blue)
- Wednesday, 26 March 2025: Ward Street, road patches on the westbound lane, between Alexander Road and Fergusson Drive (highlighted in yellow)
For more information, please visit: https://www.upperhutt.govt.nz/News/Resurfacing-Works-start-on-Ward-Street
Source: Upper Hutt City Council
20/03/25